Bid issues delay Quebec Central Railway upgrade
Bid issues delay Quebec Central Railway upgrade
Peter Black, Local Journalism Initiative reporter
peterblack@qctonline.com
While a project to bring a commuter train to the east of Quebec City could be several years away, another railway rehabilitation project in the region is well underway, but with an unexpected delay.
Postponements in the tendering process have forced a delay in work to upgrade a section of the Quebec Central Railway line between Vallée-Jonction and Thetford Mines.
Initially slated to be completed this fall, the delay may push the reopening of the line to 2027, according to a report in Beauce Média.
The project involves the third and fourth sections over a distance of 58 kilometres, the last two portions of the plan to rehabilitate 109 km of track from Lévis to Thetford Mines, for the use of predominantly cargo traffic.
The Quebec Central Railway was built in 1869 and ran from Lévis to Sherbrooke and then into the United States, a total distance of 344 km.
The Quebec government bought the line in 2007 with the aim of providing a more environmentally friendly alternative to truck cargo traffic. The first section of the project, the 33 km from Lévis to Scott, is already in operation.
The second section, the 18 km from Scott to Vallée-Jonction, is also well advanced, with five bridges rebuilt and a portion in operation between Sainte-Marie and Vallée-Jonction.
The last two sections are the most complicated and most expensive, at an estimated $440 million. The work involves, according to transport ministry information, the reconstruction of 17 bridges, replacing 102 culverts, complete reprofiling of the tracks and rebuilding 40 level crossings.
Transport ministry spokesperson Nicolas Vigneault told Beauce Média that tenders, initially called for February, were postponed until July. “These postponements were necessary, due, among other things, to the numerous questions received from bidders.”
According to the report, “Given this change to the tendering procedure, the ministry now expects work to begin in the fall of 2025. Work will be interrupted during the winter season, with commissioning scheduled for 2027.”
The Quebec government also owns the Gaspé rail line. Work to bring that line back into service after years of abandonment has been delayed due to cost issues and other complications until at least 2027.
(Editors’ note: For further information about the Gaspé rail renovations and efforts to bring passenger rail service back to the Gaspé, read this recent story by our colleagues at the Gaspé Spec.)
Bid issues delay Quebec Central Railway upgrade Read More »

