erosion

Gaspé: First step in reconfiguring York Boulevard West in the Sunny Bank sector

Nelson Sergerie, LJI Journalist

GASPÉ – The Quebec Ministry of Transport (MTQ) has issued a call for tenders for the redevelopment of York Boulevard West in the Sunny Bank sector of Gaspé.

The ministry wants to carry out the first step, which is the environmental impact study of the project, necessary to rebuild the road. In June 2022, the Sunny Bank Flood Committee won a class action against the Ministry of Transport (MTQ) and the court ordered it to carry out corrective work to maintain an adequate level of service for a flow of 600 cubic metres/second over the next six years and to build a river flow measuring station within two years.

The ministry had already committed during the proceedings to undertake about $8 million in roadwork to improve the situation within six years.

In a project notice filed with the Ministry of the Environment, the Fight against Climate Change, Wildlife and Parks for the “Redevelopment of York Boulevard West in the Sunny Bank sector in Gaspé” last fall, the MTQ detailed each of the upcoming steps for the construction site.

The ministry is aiming, in particular, to replace the bridge currently characterized by an opening of 11 metres by a bridge with a 60-metre opening as well as to dig and widen a secondary arm of the York River over 200 metres long and 54 metres wide upstream of the planned bridge.

In addition, the road embankments will be widened over 300 metres where there is a hydric environment due to the road being raised by 0.5 metres, and the ditch will be reprofiled over 400 metres along the eastern side of the Sunny Bank Street intersection.

A 70-metre long ditch and the construction of a new six-metre wide culvert are also in the plans, along with the replacement of four other culverts.

In its notice, the MTQ also proposes three other solutions as part of the impact study. The first option is the complete removal of all road embankments and the relocation of the road four kilometres upstream in a less dynamic part of the York River.

The second option is the complete removal of all road embankments and the construction of a multi-span bridge.

The last scenario, which could have a considerable impact, involves expropriating all residents in the flood zone.

According to the preliminary project schedule, the environmental impact study, a BAPE review, and obtaining the environmental decree should be completed by the fall of 2027.
In the preliminary project schedule, the environmental impact study, a BAPE and the environmental decree should be completed by fall 2027, with the environmental impact study being the first milestone in the process.

The pre-project study, concomitant with the environmental impact assessment, is scheduled for completion in spring 2028. The final preliminary design study is expected to be completed by spring 2029.
This will be followed by plans and specifications to vacate the rights-of-way between spring 2029 and spring 2032, with final authorizations to be obtained in spring 2033. The tendering and awarding of the contract will take place in spring 2033 for construction slated for summer 2033 and fall 2034.
The Ministry is not ruling out the possibility of completing the project by 2035.

Between the judgment rendered in June 2022 and the final work schedule, at least 12 years will elapse.
The road, rebuilt in 1977 which connects the Sunny Bank and Wakeham sectors, slows the flow of the York River.

Previously, it was a road at water level and, during floods, the river would overflow onto the roadway.
Raised by 1.5 metres in 1952, it was noted that the road partially blocked the river’s flow.

In 1977, the road was raised by two metres, making water evaluation even more difficult. The 2010 flood was the straw that broke the camel’s back. From December 13 to 15, 2010, approximately 246 millimetres of rain fell on Gaspé. Residents filed their lawsuit in 2013 and the court authorized it in 2015. Since its reconstruction in 1977, floods have occurred in 1977, 1980, twice in 1981, 1983, 1997, 1998, 2004, 2009, 2010, 2011 and 2017.

Gaspé: First step in reconfiguring York Boulevard West in the Sunny Bank sector Read More »

Highway 132 erosion: no decree until 2026 for action

Nelson Sergerie, LJI Journalist

GASPÉ – It will be 2026 before Quebec adopts a decree related to the Intervention Program for the Protection of Infrastructures Against Coastal Hazards by the Ministry of Transport (MTQ).

Studies have been underway since 2021 to protect, among other things, Highway 132 in the Gaspé Peninsula from erosion and coastal submersion.

Due to climate change, the ministry predicts that in Lower Saint Lawrence and the Gaspé Peninsula and the Magdalen Islands, 139 kilometres of roads will be vulnerable to erosion, and 176 kilometres will be susceptible to submersion.

In the project notice filed in July 2021, the ministry noted that recent events highlighted the need to ensure road user mobility and carry out preventive interventions. The document estimated 273 vulnerable coastal sites in the long term.

The impact study which has been in progress for nearly three years, is expected to be submitted by the end of the summer, according to the Ministry of Transport, which will indicate when the document will be available.

A series of procedures will follow before Quebec adopts the decree. Thus, the documents admissibility must be reviewed by the Ministry of the Environment, the Fight against Climate Change, Wildlife and Parks and the Bureau d’audiences publiques sur l’environnement (BAPE) will also examine the document.

Once these two steps have been completed, the report and recommendations will be analyzed by the government, and the Ministry of Transport expects the decree to be adopted in 2026.
Routine interventions by the ministry, such as repairs to retaining walls along Highway 132 on the north side of the Gaspé will continue normally.

Every new project will have to be the subject of requests for different ministerial authorizations by the MTQ.
On the north side of the peninsula, specific issues related to the inhabited areas near rivers, access difficulties due to the topography with cliffs, high exposure of the coasts to winds and waves and the road’s dependence are the main factors in the reflection.

On the south side, *mariculture exploitation, the concentration of salmon rivers and maintaining water access are highlighted in the planning. The impact study will allow for segmenting sites according to the vulnerability and the planning of the required work.

Once the decree is adopted, several steps will need to be completed for the new intervention sites.
The feasibility studies should take between four and 16 months, followed by design studies lasting 12 to 36 months, plans and specifications for 12 to 36 months and the construction.

With a decree adopted in 2026, the work for the new structures would, at best, only begin in 2028 or 2029.
Consultations are still underway for the vast project, which has been divided into four sub-regions: Lower Saint Lawrence, Northern Gaspé Peninsula, Southern Gaspé Peninsula and the Magdalen Islands.

The link for submitting comments can be found on the ministry’s website. In an interview in early 2023, the former territorial director of the Transport Ministry, Yves Berger, indicated that riverbank erosion would be the biggest transportation issue in the Gaspé Peninsula over the next 25 years. He indicated that this issue would require “major investments”.

Projects are being prepared for both the northern and southern sides of the peninsula. Mr. Berger indicated that in recent years, $20 million has been invested to address climate change.

*mariculture – a type of farming in which fish or other sea animals and plants are kept or grown for food.

Highway 132 erosion: no decree until 2026 for action Read More »

Scroll to Top