Published September 11, 2024

Nelson Sergerie, LJI Journalist

GASPÉ – The Quebec Ministry of Transport (MTQ) has issued a call for tenders for the redevelopment of York Boulevard West in the Sunny Bank sector of Gaspé.

The ministry wants to carry out the first step, which is the environmental impact study of the project, necessary to rebuild the road. In June 2022, the Sunny Bank Flood Committee won a class action against the Ministry of Transport (MTQ) and the court ordered it to carry out corrective work to maintain an adequate level of service for a flow of 600 cubic metres/second over the next six years and to build a river flow measuring station within two years.

The ministry had already committed during the proceedings to undertake about $8 million in roadwork to improve the situation within six years.

In a project notice filed with the Ministry of the Environment, the Fight against Climate Change, Wildlife and Parks for the “Redevelopment of York Boulevard West in the Sunny Bank sector in Gaspé” last fall, the MTQ detailed each of the upcoming steps for the construction site.

The ministry is aiming, in particular, to replace the bridge currently characterized by an opening of 11 metres by a bridge with a 60-metre opening as well as to dig and widen a secondary arm of the York River over 200 metres long and 54 metres wide upstream of the planned bridge.

In addition, the road embankments will be widened over 300 metres where there is a hydric environment due to the road being raised by 0.5 metres, and the ditch will be reprofiled over 400 metres along the eastern side of the Sunny Bank Street intersection.

A 70-metre long ditch and the construction of a new six-metre wide culvert are also in the plans, along with the replacement of four other culverts.

In its notice, the MTQ also proposes three other solutions as part of the impact study. The first option is the complete removal of all road embankments and the relocation of the road four kilometres upstream in a less dynamic part of the York River.

The second option is the complete removal of all road embankments and the construction of a multi-span bridge.

The last scenario, which could have a considerable impact, involves expropriating all residents in the flood zone.

According to the preliminary project schedule, the environmental impact study, a BAPE review, and obtaining the environmental decree should be completed by the fall of 2027.
In the preliminary project schedule, the environmental impact study, a BAPE and the environmental decree should be completed by fall 2027, with the environmental impact study being the first milestone in the process.

The pre-project study, concomitant with the environmental impact assessment, is scheduled for completion in spring 2028. The final preliminary design study is expected to be completed by spring 2029.
This will be followed by plans and specifications to vacate the rights-of-way between spring 2029 and spring 2032, with final authorizations to be obtained in spring 2033. The tendering and awarding of the contract will take place in spring 2033 for construction slated for summer 2033 and fall 2034.
The Ministry is not ruling out the possibility of completing the project by 2035.

Between the judgment rendered in June 2022 and the final work schedule, at least 12 years will elapse.
The road, rebuilt in 1977 which connects the Sunny Bank and Wakeham sectors, slows the flow of the York River.

Previously, it was a road at water level and, during floods, the river would overflow onto the roadway.
Raised by 1.5 metres in 1952, it was noted that the road partially blocked the river’s flow.

In 1977, the road was raised by two metres, making water evaluation even more difficult. The 2010 flood was the straw that broke the camel’s back. From December 13 to 15, 2010, approximately 246 millimetres of rain fell on Gaspé. Residents filed their lawsuit in 2013 and the court authorized it in 2015. Since its reconstruction in 1977, floods have occurred in 1977, 1980, twice in 1981, 1983, 1997, 1998, 2004, 2009, 2010, 2011 and 2017.

Scroll to Top